Next: Timers, Previous: Clocking Work Time, Up: Dates and Times [Contents][Index]
If you want to plan your work in a very detailed way, or if you need to produce offers with quotations of the estimated work effort, you may want to assign effort estimates to entries. If you are also clocking your work, you may later want to compare the planned effort with the actual working time, a great way to improve planning estimates.
Effort estimates are stored in a special property ‘EFFORT’. Multiple formats are supported, such as ‘3:12’, ‘1:23:45’, or ‘1d3h5min’; see the file ‘org-duration.el’ for more detailed information about the format.
You can set the effort for an entry with the following commands:
org-set-effort
)Set the effort estimate for the current entry. With a prefix argument, set it to the next allowed value—see below. This command is also accessible from the agenda with the e key.
org-clock-modify-effort-estimate
)Modify the effort estimate of the item currently being clocked.
Clearly the best way to work with effort estimates is through column view (see Column View). You should start by setting up discrete values for effort estimates, and a ‘COLUMNS’ format that displays these values together with clock sums—if you want to clock your time. For a specific buffer you can use:
#+PROPERTY: Effort_ALL 0 0:10 0:30 1:00 2:00 3:00 4:00 5:00 6:00 7:00 #+COLUMNS: %40ITEM(Task) %17Effort(Estimated Effort){:} %CLOCKSUM
or, even better, you can set up these values globally by customizing
the variables org-global-properties
and
org-columns-default-format
. In particular if you want to use this
setup also in the agenda, a global setup may be advised.
The way to assign estimates to individual items is then to switch to column mode, and to use S-RIGHT and S-LEFT to change the value. The values you enter are immediately summed up in the hierarchy. In the column next to it, any clocked time is displayed.
If you switch to column view in the daily/weekly agenda, the effort
column summarizes the estimated work effort for each day82, and
you can use this to find space in your schedule. To get an overview
of the entire part of the day that is committed, you can set the
option org-agenda-columns-add-appointments-to-effort-sum
. The
appointments on a day that take place over a specified time interval
are then also added to the load estimate of the day.
Effort estimates can be used in secondary agenda filtering that is triggered with the / key in the agenda (see Agenda Commands). If you have these estimates defined consistently, two or three key presses narrow down the list to stuff that fits into an available time slot.
Please note the pitfalls of summing hierarchical data in a flat list (see Agenda Column View).
Next: Timers, Previous: Clocking Work Time, Up: Dates and Times [Contents][Index]